Client: A. Žilinskio ir ko UAB
Year: 2021
Location: Sweden
LEC, in cooperation with partner A. Žilinskio ir ko, constructed a 130 kV overhead transmission line across the route Djupdalen–Rabacken–Kallamosen. The work included the installation of insulators, as well as pulling and securing overhead conductors, OPGW, and lightning protection wires. The total line length was 29.00 km.